Liner and jaw plate replacement at a cement plant

A cement plant · Karaganda Region
14 дней, wear kit delivery time
3 суток, line downtime during replacement
4 месяца, service life until next replacement

Scheduled wear part replacement in the crushing section during a shutdown.

Industry Cement industry
Project period 05.2026 - 06.2026

Problem

The crushing section stops for maintenance once a year and the window is three days. The wear part set had to arrive before the shutdown date, not after it.

Solution

The set was assembled from drawings and from measurements of the worn parts: jaw plates and cone liners. It shipped from stock two weeks before the window so the plant could receive and check the parts in advance.

Result

The replacement fitted into the maintenance window and the line restarted on time. Service life until the next replacement was recorded in the maintenance schedule together with the plant.

Spare parts supplied 2

Плиты дробящие

Jaw plates

ГОСТ 977-88

High-manganese steel Mn18Cr2, HB 210-230, наклёп до HB 500

In stock in Oskemen, 6 pcs.
Футеровки

Liners

ГОСТ 977-88

High-manganese steel Mn18Cr2, HB 200-230

Made to order, 40 days from prepayment